Aggregated Renewal & Replacement Schedules
Overview
This multi-tiered dashboard provides projected R&R data over a 10-year period in the following formats: (1) Statewide cost of all systems, (2) Statewide costs sorted by system, (3) Costs sorted by district and system, and (4) Costs sorted by attendance area and system.
Instructions
On the left bar select the systems of interest. You may also select a district and attendance area on the respective tables.
Estimated Cost to Replace is based on an assigned percentage of the facility replacement cost per system.
Anticipated Replacement Year is based on department standard system life cycle ages, as potentially modified by district personnel assessment of condition. If there is no est. cost to replace, the system has more than 10 years of anticipated life remaining.